Rectifiers and Transformers

Contractor: ABB Switzerland Ltd.


Scope of work

Engineering, procurement, construction and testing of two complete Rectifier Stations each consisting of 5 rectifier units (incl rectifiers, transformers, and controls). Each unit with a current of 85kA and 1650V DC. The SoW also includes 220kV cabling from Qatalum Power Plant to the Rectifier station.

Contact person

Helmut Joos
Project Manager
Tel: +41 58 586 8444
Fax:
Helmut Joos