When Qatar Petroleum and Norsk Hydro ASA gave their final approval for the construction of a new primary aluminium plant on July 19 2007, it was one in a series of milestones for the Qatalum project. Following the foundation stone laying ceremony on November 19 2007, a number of new milestones will be passed during the next two years.
Heads of agreement December 2004
Joint venture agreement & approval of feasibility March 2006
Investment decision October 2006
Site preparation start-up January 2007
Final approval July 2007
Construction commences November 2007
Power from grid and fuel gas for commissioning April 2009
Fuel gas for power plant gas turbines September 2009
Start-up regular anode production September 2009
Ready to commence casthouse test production October 2009
Initial power available from power plant November 2009
Potlines on stream  December 2009
Project completion August 2010